December 15, 2009 more rain!!!


My favorite big machine was back on site last week!! The Putzmeister! 9 truck loads of cement were poured last week for the floors on the first and second balconies and a retaining wall. It seems that every week we get about 2 and a half days of good weather and the rest is rain!

Also last week they began the work to tear out the ramp that went to the lower level. The new handicapped ramp will go in at this location making it easier for people with disabilities to access both the new box office and the front entrance of the Township.